On 04/18/2011 at 1AM MST we will be doing a major upgrade on our internal network infrastructure in Denver. This will increase our network capacity and will drastically increase our network perofmance and uptime.
The upgrade will include:
Upgrade cross-connect link between our Edge and Core router
Upgrade Core router supervisor engine
Upgrade Core router Switch uplink layer line card
Upgrade cross-connect link between our Core router and the end-server switches
Upgrade our Firewall Farm
We estimate that this will cause service interruptions for about 2 hours and to restore service at 3:AM MST. During this time all or partial traffic to our Denver facility systems will be disrupted.
We will be doing the similar network upgrade to our Chicago facility at a later date.
SK丹佛数据中心维护通知(20110417-0418) 2小时
SK机房将于美国时间(MST)4月17日23点(国内时间预计为4月18日13点)开始更新丹佛机房的核心路由。此次更新包括更换当前路由的管理引擎和线卡。更新将明显提升丹佛机房的网络性能,从而满足丹佛机房目前服务的需求。
此次更新大概会持续2小时,预计将于美国山区时间4月18日凌晨1点完成(国内时间预计为4月18日15点)。期间服务器将可能中断访问但不会停机。
芝加哥机房将会在之后数天内有同样的更新,届时会通知客户。
请大家知悉。
已经得到确切消息,整个丹佛机房都会中断2个小时,请大家及时准备! 已经结束。